FAQs
In this section, you can review the responses to
some of the most frequently asked questions (FAQs).
General
Regeneration is the process of renewal.
Built in the late 1960s, the existing Cambridge Road Estate has outlived its original purposes. As such, the living environment does not meet modern standards, impacting health, education and social outcomes. It is also an estate that is difficult to get around and difficult to police due to its poor lighting and layout.
The regeneration of the estate presents a significant opportunity to both increase residents' standard of living and the number of council rent homes available in the borough — so we can help more people to have the secure home they deserve.
The regeneration will deliver 2,170 new high-quality, sustainable 'greener' homes, including 1,148 affordable homes, of which 974 will be council-rented, improved community facilities, green streets, play areas and other outdoor spaces, new jobs, local training opportunities and an enhanced estate layout to provide a brighter and safer neighbourhood.
Background Papers for the Cambridge Road Estate Planning Application are available on the Kingston Council planning portal at https://www.kingston.gov.uk/downloads/download/415/cambridge-road-estate-planning-application-2002942ful---background-papers
Kingston Council is working with development partner Countryside Partnerships (part of Vistry) to deliver much-needed new homes with the 'green' credentials to match the borough's ambitious programme for more accessible, affordable and sustainable homes fit for the future.
More information about Countryside is available on the CRE regeneration website at https://www.cambridgeroadestate.com/about-countryside.
The regeneration is anticipated to be delivered over five phases.
Development projects, particularly large-scale ones like Cambridge Road Estate, involve coordinating numerous teams and stages, which makes it difficult to provide precise timelines from the outset. To ensure transparency and keep everyone informed, we share general timelines at the start and refine them with more specific dates as the project progresses. This approach acknowledges the complex nature of regeneration while keeping the community engaged with regular updates.
Construction
Demolition work for phases 1a and 1b took place in Spring 2023. Construction works for the first new blocks in Phase 1 are underway.
Block B (Daisy Court) was completed and handed over to the Council in April 2026.
Block E will follow. Hoarding works for phase 1c will begin in Summer 2026.
Construction work hours are as follows:
- 8 am - 6pm, Monday to Friday
- 8 am - 1pm, Saturday
- No working on Sundays or on Bank Holidays
We will aim to minimise disruption through a number of ways, including:
- Strictly adhering to hours of work.
- Managing the timing and routes of vehicle deliveries.
- Monitoring dust, noise and vibration.
- Reducing noise and vibration through the use of specially designed machinery.
- Reducing dust through water spraying.
- Site security.
- Careful use of lighting.
These commitments are secured by way of a planning condition.
Considerate Constructors Scheme:
Countryside is registered with the Considerate Constructors Scheme, an independent organisation established in 1997 to raise standards in the construction industry. All sites are regularly and independently inspected and scored against the Scheme's Code of Considerate Practice.
The only access and exit for construction traffic will be via either Cambridge Road or Hawks Road.
If you have any construction-related queries, contact Countryside at:
Email: WL.CRE@vistry.co.uk
Telephone:
Out of Hours Security on FREEPHONE 0800 195 4071 (Site working hours are 8 am to 6 pm, Monday to Friday, and 8 am to 1 pm, Saturdays)
Noticeboards with contact details are also available on on-site hoardings.
Yes.
Upcoming milestone events, activities and achieved targets will continue to be communicated to residents and neighbours.
Newsletters, website updates, social media and other related communications will continue throughout the regeneration period.
Countryside is the UK’s leading mixed-tenure developer through its two divisions, Partnerships and Housebuilding.
As each phase is brought forward, Meet the Builder sessions are held at Cambridge Road Estate, with exhibition boards providing information about the regeneration programme. Residents are invited to attend, ask questions and speak directly with the project team.
The exhibition boards from the Meet the Builder sessions are available for review on this website at https://www.cambridgeroadestate.com/regeneration/key-info.
More information about Countryside is available at https://www.cambridgeroadestate.com/about-countryside.
Regeneration phases
Phase 1 is divided into 3 subphases as below:
- a: Tadlow, Piper Hall
- b: Ely Court, Washington Rd (1–13), Willingham Way (2–14 evens)
- c: Fulbourn, Comberton, Grantchester
Phase 2 is divided into 2 subphases
- 2a: Westwick, Chesterton Terrace (houses)
- 2b: Connington, Fordham, Caldecote, Chippenham, Burwell
Phase 3:
Madingley, Oakington, Graveley, Croxton, Harston, Brinkley, Burritt Road (houses).
Phase 4:
Willingham Way (houses 1–21 odds), Cambridge Grove Road (Flats 47, 47a, 47b, 49, 49a, 49b), Cambridge Grove Road (30–50 evens), Foxton, Impington, Shelford, Duxford.
Phase 5:
Franklin Close, Willingham Way (houses 16–30 evens, 23–49 odds), Cambridge Grove Road (2–28 evens), Cambridge Grove Road (Flats 51, 51a, 51b, 53, 53a, 53b), Vincent Road, Stapleford, Childerley.
CRE masterplan map
This masterplan shows the proposed block locations in the regenerated neighbourhood.
The anticipated demolition start dates for each phase are as follows:
Anticipated demolition timelines for the start of each phase
Phase 1 commenced spring 2023
Phase 2 is expected to commence in early 2027
We will keep the community updated on commencement dates for phases 3, 4 and 5 when these are known.
Phase 1
Phase 1 commenced in late 2022 and will deliver 452 homes, including 357 for council rent.
Phase 2
A hybrid planning application was approved in July 2022. This included the detailed plans for Phase 1 and an outline for plans for Phases 2–5, to deliver around 2,170 new homes.
The detailed elements of Phase 2 were reserved for later approval. Construction on Phase 2 cannot begin until the detailed elements are approved through an RMA.
Throughout 2024/25, we developed the detailed plans with input from members of the public. The planning application was submitted in August 2025. We await consent for the detailed application.
Blocks in Phase 2 contain a mixture of social rent, shared equity and private market homes. The distribution of these homes within the three Phase 2 blocks will be confirmed as more detailed designs emerge.
Community facilities
Queen Mary Hall has been identified as the temporary community centre to replace Piper Hall until the new community centre for the redeveloped neighbourhood is completed in phase 1. This is to ensure facilities remain available in the neighbourhood. Queen Mary Hall is located very close to the Cambridge Road Estate, positioned directly opposite, on Cambridge Gardens.
Refurbishment of Queen Mary Hall is complete and this new community facility is now in use.
Social value
The UK Green Building Council gives a clear definition: “Social value is created when buildings, places and infrastructure support environmental, economic and social wellbeing".
There are four key themes that our social value strategy is responding to. These are:
- Improving health and wellbeing
- Investing in communities (including the community chest* element)
- Supporting employment, education and skills
- Creating opportunities for young people
*The Community Chest fund provides £50,000 each year (£75,000 in the first year) for resident-supported projects, helping to strengthen community involvement and wellbeing.
Tree protection
The regeneration plans have been carefully designed to allow a number of existing trees to be retained. Measures will be put in place to protect these trees at all stages of the construction works.
Tree protection will be in line with the British Standard BS5837. This standard details the steps that should be taken to ensure trees are appropriately and successfully retained when a development takes place.
Fencing will be erected around the trees, preventing pedestrian and vehicular traffic.
Materials storage will be located away from the trees.
Opportunities for local people and businesses
A significant employment and training package has been secured which provides Kingston Council with financial contributions to support employment support services, skills development, employment and apprenticeships, and local businesses.
Up to 400 sustainable jobs in construction will be filled by local people. This includes jobs of at least 26 weeks in duration.
Approximately 100 apprenticeships covering levels 2–7 for local people or students.
Up to 500 local youth employment opportunities for residents and students such as industry placements, internships, traineeships, work experience and mentoring.
Opportunities will be provided for local businesses to supply goods and services to the construction with the ambition to enable at least 10% of the value to be sourced locally. Help will be provided to local businesses to enable them to tender for opportunities.
Contacts
If you have any construction-related queries, please contact Countryside using the contact details on our Contact page at https://www.cambridgeroadestate.com/contact.
If you have any other enquiries about the regeneration, please find the contact details on our Contact page at https://www.cambridgeroadestate.com/contact and get in touch.
For independent advice, please find the contact details on our Contact page at https://www.cambridgeroadestate.com/contact.